Procurement
How to Order Custom Windows and Doors from an Overseas Manufacturer
Ordering custom windows and doors overseas requires more than comparing prices. This practical guide explains how US project teams should coordinate drawings, specifications, final field dimensions, approvals, production, delivery and unloading before placing an order.

Quick answer: A successful overseas window and door order is managed as a project, not a catalog purchase. Define the openings and performance criteria, compare quotations on the same scope, review shop drawings, verify final field dimensions, approve a controlled specification, and confirm delivery and unloading before production begins.
Custom architectural windows and doors can give a project more flexibility in size, configuration, finish, and cost. They also create coordination risks that do not exist when buying a stocked local unit. For a US contractor, architect, or owner, the central question is not simply “Can this be manufactured?” It is “Can the final configuration be documented, verified, delivered, and installed without avoidable surprises?”
1. Start with a complete project brief
A useful inquiry should identify the project location, building type, approximate schedule, product types, quantity, opening sizes, preferred finish, operating direction, glazing priorities, and the local team responsible for installation. Architectural plans, elevations, window schedules, photographs, and rough-opening dimensions are all useful. Early dimensions can be preliminary, but they must be labeled clearly so they are not mistaken for production dimensions.
Tell the manufacturer which requirements are mandatory and which are preferences. Examples include sightline goals, thermal-break frames, glass appearance, safety glazing locations, egress considerations, sill conditions, screens, hardware, coastal exposure, and accessibility. Requirements vary by jurisdiction and configuration, so the project’s qualified local professional should identify the applicable code and approval path.
2. Compare scope—not just price
Two quotations can show similar totals while covering very different work. A useful comparison asks:
- Are frame series, operating types, glass build-ups, finishes, hardware, screens, and accessories identified?
- Are quantities and unit marks coordinated with the drawings?
- Does the price include crating, inland freight, ocean freight, customs clearance, duties, and final delivery?
- What is excluded—installation, unloading, field measurement, sealants, flashing, structural supports, or electrical work?
- What payment, revision, production, damage-claim, and warranty terms apply?
A low number is not useful if essential scope appears later as an extra. Ask for an itemized proposal and a written definition of the delivery term and named destination.
3. Review the technical direction before committing
Energy and comfort decisions should be based on the complete fenestration assembly, not on glass marketing language alone. U-factor describes heat transfer; lower values generally indicate better resistance to heat flow. Solar heat gain coefficient (SHGC) describes admitted solar heat; the appropriate value depends on climate, orientation, shading, and design goals. The US Department of Energy and NFRC both emphasize these whole-product metrics.
Do not assume that one published value applies to every size, glass option, frame, or operating type. Request documentation relevant to the proposed configuration, and have the project professional evaluate it against local requirements.
4. Treat shop drawings as the control document
Shop drawings should translate the design intent into manufacturable units. Review overall frame sizes, unit marks, panel configuration, handing and opening direction, sill and threshold, frame depth, mullions, hardware, glass, finish, drainage, screens, and interfaces with adjacent construction.
The manufacturer can coordinate the product, but it cannot see concealed framing or take responsibility for conditions it has not verified. A qualified local contractor or design professional should confirm field dimensions, substrate conditions, structure, waterproofing strategy, tolerances, and installation access. Record revisions and approve one final drawing set so production is not based on an outdated email or sketch.
5. Verify final dimensions before production
Custom units should not be released from preliminary dimensions. Measure each opening after the relevant construction is stable, check width and height at multiple locations, verify square, plumb, level, and sill condition, and confirm the intended installation clearance. Do not deduct a universal allowance without coordinating the product’s installation detail and the project conditions.
For large doors, also confirm floor buildup, finished floor elevation, drainage, recesses, structural header deflection, and a feasible path from the delivery vehicle to the opening.
6. Freeze the commercial and technical scope
Before payment or production, the final order should identify the approved drawings, product schedule, finish, glass, hardware, included accessories, price, payment milestones, production basis, delivery term, named destination, unloading responsibility, damage-reporting procedure, and warranty terms. If the order is DDP, confirm what DDP means for this transaction and whether the buyer still needs to supply information or documentation for customs and delivery.
7. Plan delivery before the units leave the factory
Large crates require more than a street address. Confirm truck access, turning space, overhead restrictions, road limitations, appointment requirements, storage location, crew, forklift or crane capacity, fork length, rigging, and weather protection. Standard delivery commonly ends with the goods available for unloading from the arriving vehicle; unloading and installation should be stated separately in writing.
A practical pre-order checklist
- Project location and applicable local review identified
- Plans, schedule, photos, and preliminary openings submitted
- Product configuration and performance direction documented
- Itemized quotation and exclusions reviewed
- Final field dimensions verified locally
- Shop drawings approved and revision locked
- Delivery term, address, access, and unloading plan confirmed
- Payment, damage reporting, replacement, and warranty terms accepted
Frequently asked questions
Should I order before the rough openings are complete?
You can begin design and pricing from plans or preliminary dimensions, but production dimensions should be verified by the qualified local team after the relevant conditions are stable.
Who confirms compliance with local code?
The manufacturer supplies product information for the proposed configuration. The architect, engineer, contractor, or other qualified local professional determines suitability for the project and jurisdiction.
Does DDP include installation?
No. DDP is a trade and delivery term, not an installation service. Unloading and installation must be defined separately.
Start with the information you already have
MERUZY provides project-specific design coordination and quotations for custom windows, sliding doors, folding doors, pivot doors, stairs, and railings. Send your plans, window schedule, photographs, or rough-opening dimensions to begin a documented review. See how the MERUZY process works or request a free design and quotation.
Editorial note: This article provides general project-planning information, not architectural, engineering, code, customs, or legal advice. Final requirements and responsibilities are governed by the approved project documents and signed order.
Editorial review
Prepared for project education and reviewed for consistency with MERUZY’s current supply-only design, quotation and delivery process. Project-specific requirements are governed by approved documents and the formal order.
Reviewed by: MERUZY Project Coordination Team
Sources and further reading
QUESTIONS & DISCUSSION
Ask a question or add to the discussion
Have a question about this guide? Ask it here. The MERUZY team and other project professionals may respond.
Do not include private project information, addresses, drawings, pricing, order details, phone numbers or email addresses in your public comment.